Background
Mercury was appointed to deliver PAR11, a large-scale data centre facility in Paris with a capacity of 19.6 MW. The project required the coordination of multiple MEP trades across a complex build programme. Mercury partnered with VisiLean to digitise their production planning and bring lean principles into the day-to-day execution of the project.
Challenges
- Coordinating multiple MEP trades across overlapping work zones
- Managing design changes and material delivery flows in real time
- Limited cross-trade visibility leading to clashes and rework
- Manual reporting and fragmented planning tools causing delays in decision-making
Solution
VisiLean was deployed as the central production management platform, enabling:
Digital Last Planner System � Weekly work planning sessions moved from spreadsheets to VisiLean, giving every trade a shared view of commitments and constraints.
Lookahead Planning & Programme Management � 6-week lookahead plans were managed collaboratively, with constraints tracked and resolved before they caused delays.
Constraint Management � All blockers (design, materials, access, prerequisites) were logged, assigned owners, and tracked to resolution.
Live Reporting & Dashboards � Real-time dashboards via Power BI replaced manual weekly reports, giving leadership instant visibility into PPC, constraints, and programme health.
Collaboration & Transparency � All trades and subcontractors accessed the same live plan, eliminating information silos and improving coordination.
Outcomes & Impact
- Early completion: Practical completion achieved three months ahead of programme
- Planning reliability: PPC improved from 52% to 85-90%
- Reduced waiting time: Trade waiting reduced from 18% to less than 8%
- Reporting efficiency: Weekly reporting time reduced from 6 hours to zero with automated dashboards
- Programme agility: Rapid re-planning capability when design changes occurred
- Cost avoidance: Significant reduction in rework and idle crew costs
Key Learnings
- Real-time visibility into production status is essential for large-scale MEP coordination
- Digital Lean tools must be embedded into daily workflows, not used as a reporting afterthought
- Transparency across trades builds trust and reduces defensive scheduling
- Standardising the planning process across projects enables continuous improvement and knowledge transfer